Project case

YKK Building Phase 3, No. 7 San Ping Circuit

Building type
Operational commercial and industrial building
Project type
Commercial & Industrial
District
Tuen Mun
Scope of works
Commercial-building roof and building-services waterproofing
Top-down aerial view of YKK Building in Tuen Mun, showing a green court, mechanical equipment and pipework

Engineering record

Project background and problem

Roof equipment, pipework and daily operations required the refurbishment to be divided into manageable zones.

Principal scope of works

  • 01Zoned roof waterproofing
  • 02Detail treatment around building services and pipework
  • 03Construction and completion records

System or material approach

Waterproofing methods arranged by roof zone and around equipment and pipework.

Inspection, acceptance or project records

The existing public record includes a phased-work video and photographs of the work stages and completed membrane. No independently publishable test report was found in the project source.

Updated
Content owner
Proficient Waterproofing & Engineering Ltd.
Reviewed by
Proficient Waterproofing Technical Team

This page was reviewed against existing public case records, site photographs and verifiable project information. Contract tests, acceptance, warranty and completion dates are stated only when public evidence is available.

Project requirements

Project Overview

YKK Building Phase 3, No. 7 San Ping Circuit is located in Tuen Mun. The principal scope was commercial-building roof and building-services waterproofing. The works also addressed maintaining building operations while works proceeded in stages.

The approximately 4,000 m² scope covered roofs, building services, pipework surrounds and related details.

Works were divided into manageable zones around the existing equipment and daily operations, making the refurbishment programme easier to monitor.

Construction record

Arranged by work sequence
Elevated view of YKK Building in Tuen Mun, with the rooftop YKK sign, mountains and railway behind
YKK Building Phase 3, No. 7 San Ping Circuit site record 0101 / 08
High-angle view of the weathered roof at YKK Building, Tuen Mun, with a worker beside wall-mounted pipework
YKK Building Phase 3, No. 7 San Ping Circuit site record 0202 / 08
Three workers among rooftop pipes, cable trays and a water tank at YKK Building, Tuen Mun
YKK Building Phase 3, No. 7 San Ping Circuit site record 0303 / 08
Three workers treating a grey roof surface beside large pipes and equipment plinths at YKK Building, Tuen Mun
YKK Building Phase 3, No. 7 San Ping Circuit site record 0404 / 08
High-angle view of the light-grey roof, cooling equipment and pipework at YKK Building, Tuen Mun
YKK Building Phase 3, No. 7 San Ping Circuit site record 0505 / 08
High-angle view of the broad light-grey roof and wall-side pipework at YKK Building, Tuen Mun
YKK Building Phase 3, No. 7 San Ping Circuit site record 0606 / 08
Aerial view of YKK Building in Tuen Mun, showing rooftop equipment, pipework, openings and pale roof surfaces
YKK Building Phase 3, No. 7 San Ping Circuit site record 0707 / 08
Top-down aerial view of YKK Building in Tuen Mun, showing a green court, mechanical equipment and pipework
YKK Building Phase 3, No. 7 San Ping Circuit site record 0808 / 08