Project case
YKK Building Phase 3, No. 7 San Ping Circuit
- Building type
- Operational commercial and industrial building
- Project type
- Commercial & Industrial
- District
- Tuen Mun
- Scope of works
- Commercial-building roof and building-services waterproofing

Engineering record
Project background and problem
Roof equipment, pipework and daily operations required the refurbishment to be divided into manageable zones.
Principal scope of works
- 01Zoned roof waterproofing
- 02Detail treatment around building services and pipework
- 03Construction and completion records
System or material approach
Waterproofing methods arranged by roof zone and around equipment and pipework.
Inspection, acceptance or project records
The existing public record includes a phased-work video and photographs of the work stages and completed membrane. No independently publishable test report was found in the project source.
Project requirements
Project Overview
YKK Building Phase 3, No. 7 San Ping Circuit is located in Tuen Mun. The principal scope was commercial-building roof and building-services waterproofing. The works also addressed maintaining building operations while works proceeded in stages.
The approximately 4,000 m² scope covered roofs, building services, pipework surrounds and related details.
Works were divided into manageable zones around the existing equipment and daily operations, making the refurbishment programme easier to monitor.
Construction record
Construction Photographs