Project case
Shell Oil Depot, Tsing Yi
- Building type
- Industrial facility / oil depot
- Project type
- Commercial & Industrial
- District
- Tsing Yi
- Scope of works
- Industrial-facility waterproofing

Engineering record
Project background and problem
An approximately 9,700 m² industrial refurbishment required removal of existing floor and wall finishes and a redesigned approach to roof, external-wall and drainage waterproofing under operating-site constraints.
Principal scope of works
- 01Removal and reinstatement of existing floor and wall finishes
- 02Redesign and construction of roof and external-wall waterproofing
- 03Drainage details and completed-surface records
System or material approach
Waterproofing and drainage arrangements redesigned for the roof, external walls and site drainage; no single product model is stated in the public case.
Inspection, acceptance or project records
Scaffold, substrate, material, roof-work, detail and completed-condition photographs form the published project record.
Project requirements
Project Overview
Shell Oil Depot, Tsing Yi is located in Tsing Yi. The principal scope was industrial-facility waterproofing. The works also addressed coordination of operations, external walls, roof and drainage.
Existing floor and wall finishes were removed before waterproofing and completed surfaces were rebuilt around the drainage and operating conditions of the facility.
The works also established effective long-term drainage. Records cover access scaffolding, materials, roof works, details and completed external surfaces.
Construction record
Construction Photographs